We are delighted to share great progress on our Heybridge site, across all 3 phases of the project. With the first phase completed we are steadily working on phases 2 and 3.

With a naturally high-water table and an exceptionally wet winter, this site has posed some real earthworks challenges. Despite this, our team has delivered impressive progress, staying on programme and maintaining consistent quality.

We’re pleased to share the key milestones achieved so far:

Phase 1:
✅ Whole Phase Complete

Phase 2:
✅ 100% Adoptable Roads and Sewers Installed
✅ 65% Oversites Completed
✅ 40% external works completed with residents moved in.

Phase 3:
✅70% Adoptable Roads and Sewers Installed
✅45% Oversites Completed

A huge thank you to everyone involved for your hard work and commitment. We’re excited to see this development continue to grow and evolve in the months ahead! 💙