St. Mary’s Island is a former submarine base and the site incorporates 150 acre residential development that forms part of the 350 acre Chatham Maritime regeneration project.
Challenge
- Tidal water table adjacent to River Medway
- Extensive underground structures, some up to 20m deep
- Pumped foul drainage – With development just above sea level all foul drainage requires pumping off site,
Solution
- Detailed planning was required to be co-ordinated with tides and dewatering activity.
- Tamdown worked with Countryside Properties to redesign piling arrangements to allow underground structures to remain in place and avoid additional costs.
- Extensive discovery and preparation was required to ensure the existing pumping system was not impacted during connections and adjacent works.
Outcome
- Over the 15 years Tamdown delivered onsite we worked closely our customer to ensure quality delivery.
- The close partnership ensured we resolved any challenges together and agreed the best way forward for both delivery and programme.