Tamdown has a long history working on the Beaulieu site going back to 2010 which will see us deliver over 1000 units across eight phases. Most recently we have been delivering Zone Q which sees a 122 units with 550m of estate road constructed within a 140 week programme.

Challenge

  • Build location was being utilised as a site car park for all the other phases at the Beaulieu development, so relocating the car park was a critical first step
  • Site was previously quarried for sand and gravels and replaced with engineered fill up to 15m deep.
  • Whole site needed piled foundations which required an optimum cut & fill and pile mat strategy to be produced
  • Working in close proximity to occupied residential properties

Solution

  • Planned and co-ordinated approach to phasing the cut and fill – ensuring this was completed first to enable the pile mats to be installed without the need for additional import of material
  • Tamdown has completed seven previous phases on the development and have built up a good working relationship with Countryside
  • Precise planning and careful delivery to ensure works were carried out with the minimum of desruption and the ensured safety of the local community

Outcome

  • Earthworks completed to plan and pile mat strategy provided appropriate and timely access for the piling rig to the first stages of build
  • Site is being run well, Tamdown on programme with good quality work being completed
  • Safe and quality delivery building and maintaining strong reputations for Countryside and Tamdown